- Client: Northern Gas Networks
- Value: £120,000
- Duration: 12 weeks
Saltwick offtake was under going a complete site rebuild including pipeline diversions, electrical & instrumentation upgrade and a new flow metering philosophy.
Simkiss were awarded phase 1 of the project, to supply, install and deliver the telemetry kiosk, switchgear kiosk and DNO intake kiosk.
![Saltwick Offtake 1](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000440-e1556292313230-1-1024x768.jpg)
![Saltwick Offtake 2](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000436-e1556292335755-1-1024x768.jpg)
![Saltwick Offtake 3](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000435-e1556292355832-1-1024x768.jpg)
![Saltwick Offtake 4](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000431-e1556292374438-1-1024x768.jpg)
![Saltwick Offtake 5](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000343-e1556292391327-1-1024x768.jpg)
![Saltwick Offtake 6](https://www.simkiss.co.uk/wp-content/uploads/2019/04/P1000342-e1556292293175-1-1024x768.jpg)
Our strategy was clear from the outset, appointing an approved HIAB contractor to ensure a safe and smooth operation to transport from Manchester to Whitby (Newcastle-Upon-Tyne) on completion
The kiosks consisted of a vast amount of switchgear and control panels which were intricately planned out with attention to detail to ensure they were accessible and aesthetically pleasing on the eye.